System Investigation
Our technicians investigated the four compromised units and assessed their condition to determine the appropriate replacement strategy.
Contact Info
Precision Medical needed to replace four 30-year-old Trane RTUs with new, energy-efficient units. Lehigh HVAC assessed the existing systems, recommended replacement, and executed the project according to industry standards.
The team safely removed the old units, carefully installed the new ones, and completed necessary electrical corrections and ductwork modification — all within a tight three-day window.
The project required replacing four outdated RTUs with more energy-efficient units, along with electrical corrections. The challenge was to complete the whole project in just three days with fully operational, reliable units.
Lehigh HVAC combined system assessment, equipment replacement, and electrical corrections into one coordinated project.
Our technicians investigated the four compromised units and assessed their condition to determine the appropriate replacement strategy.
We advised Precision Medical on the replacement requirements and coordinated the work needed to remove and replace all four aging rooftop units.
We removed the existing equipment, installed the replacement RTUs, and completed the required electrical corrections smoothly.
We tested the completed systems and electrical work to verify proper operation before completing the project.
A closer look at the four-RTU replacement completed by the Lehigh HVAC team at Precision Medical.
Lehigh HVAC completed the full scope within three days and restored the rooftop HVAC systems to operational service according to the client's requirements.
Replacing four compromised rooftop HVAC units.
Investigating existing equipment before replacement.
Addressing electrical issues identified during the project.
Testing the completed systems before project handover.
Explore more commercial projects completed by our experienced team.