How Lehigh HVAC Replaced Four Rooftop Units in Three Days

How Lehigh HVAC Replaced Four Rooftop Units in Three Days

Replacing rooftop units at a commercial property involves more than mounting the unit and coordinating electrical connections. It requires hours of assessment, step-by-step installation, and then a detailed quality assurance checklist. A slight mistake at any stage can be significantly costly and lead the client’s complete investment to the drain.

Lehigh HVAC, one of the professional HVAC agencies in Pennsylvania, recently carried out four RTU installations at a commercial property, Precision Medical. The project involved replacing old, 30-year-old Trane equipment. This guide explores what goes into commercial RTU projects and how Lehigh HVAC completed the one.

Why Replacing Multiple RTUs Requires More Coordination

Replacing one rooftop unit involves several connected tasks. A four-unit project increases the amount of equipment, installation work, and coordination required.

Here is what we considered for this project.

  • The condition and specifications of each existing unit.

  • Compatibility of replacement equipment with existing connections.

  • Electrical requirements and any necessary corrections.

  • Rooftop access and equipment removal arrangements.

  • Ductwork connections and modifications.

  • Testing and commissioning requirements.

The Process Behind Commercial RTU Replacement

Individual projects may have different requirements. However, here is a general approach we follow.

1. Assessing Existing Units Before Replacement

The first step is understanding what is currently installed. We inspect each rooftop unit rather than assuming all four have identical conditions. Important details we notice include equipment age, model information, physical condition, electrical connections, and existing ductwork arrangements. This assessment helps us identify differences that may affect replacement. For example, two units installed in the same building may have different connection requirements or serve different areas.

2. Confirming Electrical and Mechanical Requirements

A new rooftop unit must work with the building's existing infrastructure or receive the necessary modifications. Electrical coordination is particularly important. That’s why we verified that the available electrical supply and connections are suitable for the replacement equipment. Identified issues were addressed as part of the planned work. The team also assessed the ductwork, as existing connections may require modification to match the new equipment and maintain suitable airflow.

3. Coordinating Equipment Removal and Installation

Removing multiple rooftop units requires a planned approach to equipment handling and installation access. At our project on Precision Medical, we answered critical questions clearly before starting the project. Here is what we answered.

  • How existing equipment will be removed.

  • How replacement units will reach the roof.

  • Whether rooftop access creates logistical restrictions.

  • Which installation tasks depend on other work being completed.

  • How the building's operations may be affected during the replacement.

4. Testing in the Project Schedule

Installation is not complete simply because new equipment has been positioned and connected. Each replacement unit needs appropriate startup checks and commissioning. This is why we verified electrical connections, equipment operation, controls, and relevant mechanical components before handover. For projects involving several units, testing each system matters. A successful startup of one RTU does not confirm that the other three are operating correctly.

Plan Your Commercial RTU Replacement Before Equipment Fails

Lehigh HVAC provides commercial RTU replacement services in Pennsylvania. We plan, evaluate, install, and test the newly installed unit against ASHRAE standards for commercial HVAC services. If you have a commercial HVAC project for which you require reliable service providers, feel free to contact us for an estimate.

Frequently Asked Questions:

The timeline depends on the number of units, equipment specifications, rooftop access, electrical work, and ductwork requirements. Some projects can be completed within a few days, while more complex replacements take longer.

It is possible, depending on site conditions and project scope. Lehigh HVAC completed a four-unit replacement at Precision Medical within three days, including electrical corrections and ductwork modifications.

Electrical requirements should be assessed before installation. Any necessary corrections must be coordinated with the replacement work to support safe and proper equipment operation.

Not always. Existing ductwork may be suitable for the replacement equipment, but contractors should inspect connections and requirements before installation to identify necessary changes.

They should verify electrical connections, equipment startup, controls, and relevant mechanical operation. Commissioning helps confirm that each replacement unit is functioning properly before handover.
Share this post: